A Construction Change Order Can Move the Draw Date, Not Just the Budget

November 28, 2026

By Don McClain | Founder & Principal, Medro Advisors Track proposed, approved and eligible-for-draw amounts separately. A $45,000 change funded from contingency may still require owner cash if it comes due before lender approval. Record who authorizes the change, its inspection date, and when the cash actually becomes available; update the draw schedule before signing.