A Finished Buildout Can Still Have a Month With No Operating Income

November 26, 2026

By Don McClain | Founder & Principal, Medro Advisors Archive update: Put each opening gate on the calendar: utilities, applicable inspections, equipment commissioning and first date the space can actually serve customers. If monthly carrying cost is $12,000, a two-month gap between construction completion and opening ties up about $24,000 before other costs. Ask the project team to identify the gate that can move the opening date. Share the remaining costs and current dates with FCC.