Call Fast Commercial Capital305-396-3900833-828-FASTinfo@fastcommercialcapital.com
A Medro Advisors CompanyLed by Don McClain, Founder & Principal of Medro Advisors
All insights

FCC Updates

Construction Financing Has to Carry the Project Through Its Exit

Source archive date · September 28, 2026

A construction financing request is often introduced with a purchase price, a building budget, and a projected completed value. Those figures matter, but they do not show whether the project has enough capital to reach completion and repay the loan.

Original publication. Historical wording and references are retained.

09/28/26

Construction Financing Has to Carry the Project Through Its Exit

By Don McClain | Fast Commercial Capital

A construction financing request is often introduced with a purchase price, a building budget, and a projected completed value. Those figures matter, but they do not show whether the project has enough capital to reach completion and repay the loan.

A construction lender is financing a changing asset. At closing, some of the value may exist only in plans and projections. During the loan, costs are incurred, work is inspected, and proceeds are advanced in draws. At completion, the property must be sold, occupied, leased, or refinanced. The financing structure has to work through every stage.

The full budget goes beyond the building contract

The contractor’s price may be the largest cost, but it is rarely the only one. Land and existing debt, site work, utility connections, design, engineering, permits, insurance, taxes, lender costs, interest, and contingency all belong in the project budget. Depending on the asset, the sponsor may also need cash after construction for marketing, sales, or lease-up.

Every cost needs a funding source. A sponsor should know how much equity must be contributed, when it must be available, and what the loan will advance. The budget should also identify who supplies additional cash if costs exceed the plan.

A contingency helps absorb changes. Its adequacy depends on how complete the plans and bids are and how much uncertainty remains at the site. Treating it as unused profit before construction is complete can leave the project exposed when a change order arrives.

Draw timing is a cash-flow issue

Construction loans commonly release proceeds in stages after work has been completed and reviewed. Contractors and suppliers, however, have their own payment schedules. The sponsor may need to fund the interval between an invoice and an approved draw.

That timing should appear in a cash-flow forecast, not just in the loan agreement. The forecast should track committed costs, expected invoices, equity contributions, loan draws, remaining contingency, and cash available to complete the project.

A financing commitment can be large enough in total and still create a cash shortage at a particular moment. That is why project liquidity deserves as much attention as the headline loan amount.

Completion and repayment are separate tests

Finishing construction does not automatically repay the construction loan.

For a property intended for sale, the sponsor needs supportable sale prices and a realistic period to close transactions. For an income property, completion may be followed by lease-up and operating history before permanent financing is available. For an owner-occupied building, the business must be able to support the proposed long-term debt.

The projected refinance should be tested against likely value, operating income, debt service, and loan proceeds. If the takeout loan is smaller than the construction balance, the sponsor must identify how the difference will be paid. If the sale or refinance takes longer, the sponsor must be able to carry the project through the delay.

Bring the risks into the discussion early

Permits, utility work, site conditions, insurance, contractor capacity, and changes to plans can affect both cost and schedule. None is improved by leaving it out of the financing presentation.

A strong construction request states what is complete, what remains, who is responsible for each open item, and how the budget accommodates uncertainty. Once the loan closes, the same discipline continues through cost-to-complete reporting and early communication when the facts change.

At Fast Commercial Capital, we evaluate construction and transitional commercial real estate requests in the context of the full transaction. The key question is whether the capital structure gives the sponsor a credible path through completion and exit.

I discussed the broader construction and development question in a recent article for Medro Advisors. It also appears in two new chapters of my forthcoming book, Funded.

Related reading

Medro Advisors news:
https://sites.google.com/view/medroadvisors/news-media

Full construction and development article:
https://dlmcclain1.medium.com/what-makes-a-construction-or-development-project-financeable-c0acbced8343

Fast Commercial Capital LinkedIn discussion:
https://lnkd.in/p/eWA9yveJ

Fasty Funding on operating cash during construction:
https://lnkd.in/p/ej6_KDib

Alianza Partners on acquisition plans involving improvements:
https://lnkd.in/p/eYVZk3a7

Capital Advisory Report:
https://www.linkedin.com/pulse/capital-advisory-report-fastcommercialcapital-dbrue

Don McClain
Fast Commercial Capital
Part of the Medro Advisors environment