By Don McClain | Founder & Principal, Medro Advisors If bridge debt costs $16,000 per month and taxes, insurance and operating shortfalls add $9,000, a three-month exit delay consumes $75,000 before any extension fees. Build that number into the bridge budget. Then ask which extension conditions are actually written into the loan, who owns the refinancing or sale milestones, and when the team must start the backup. A projected sale price cannot cover a shortfall that comes due before the sale.